Hi Rahul Thank you very much for the response! - Our current version of Production module (Production II I believe it is) does not allow us to specify time, only date. I agree, it looks like there is an internal default time of 12am hardcoded in AX but I wonder where it is and if it can be changed to say 11:59pm instead. - Our plant is generally closed on weekends so in the calendars assigned to resources there is no capacity allowed for these days. So if we say the delivery date is Monday, AX currently says production needs to happen on Friday (which is not what actually happens). I would be very interested to see if anybody who uses the same version of Production module have experienced the same issue and if they found a way to resolve it without upgrading to a next version of the software. Thanks, Dmitry Yakimenko
↧